What is your production lead time for streetwear apparel?
Lead time, planned backwards
Three weeks of bulk is not the risk. The risk is that it sits between a 2–3 week sample and a 2–5 week freight, so a fixed launch date needs 7–11 weeks from decision.
| Stage | Typical time | Who controls it |
|---|---|---|
| Sampling + one adjustment round | 2–3 weeks | Your approval speed |
| Bulk, ≈100 pieces | About 3 weeks | Starts only at approval |
| Freight | 2–5 weeks by sea, days by air | Mode you choose |
| Decision to shelf | 7–11 weeks | — |
| Where time is lost | Mechanism | Lever |
|---|---|---|
| Fabric not in stock | A mill order sits before cutting; sewing capacity cannot recover it | Choose a stocked fabric, or order fabric during sampling |
| Wash is a sequence | Trial → approval → bulk; a second wash does not run in parallel | One wash for the first order |
| Approval rounds | The clock starts at approval, so extra rounds add to the front | Agree the correction list in one pass |
| Decoration set-up | Screens and embroidery programs are built per colour, per position | Fewer positions, proven on the sample fabric |
Rule of thumbIf the launch is under seven weeks away, the only levers left are stocked fabric and a decoration method already proven on it. Everything else is arithmetic.