What is your production lead time for accessories?
Tooling sits outside the three weeks, in front of it.
Where a metal part is cast or moulded, the mould is built first and production cannot be scheduled until it exists. The three weeks only starts once the part exists in its final form.
| Part source | What happens first | Where the 3 weeks starts |
|---|---|---|
| Existing mould | sampling only | at approval |
| New mould | tooling, then sampling | after tooling |
Rule of thumbIf the date is fixed, design around an existing mould. A new mould is not a delay you can negotiate down.