What is your production lead time for cargo pants?
Hardware arrives before cutting, so a late hardware change blocks the line instead of slowing it.
Sliders, buckles and snaps are bought against the sample specification. Changing one after approval is a new purchase order, and the cutting table waits for it — because you cannot cut pockets you cannot finish.
Sequence: hardware → cutting → sewing → finishing. A change in step one stops step two, rather than adding time to the end.
Rule of thumbSettle pocket layout and hardware on the sample. Both are cut-critical, both are cheap to change early and expensive to change late.