What is your production lead time for bags?
Assembly is handwork that only starts when both hardware and lining have arrived.
Hardware finish, zip length and lining material are all bought to the sample specification. Two of the three are usually long-lead, and neither can be substituted without re-approval.
What does not help: adding sewers. Hand assembly is paced by the arrival of components, not by the number of hands available.
Rule of thumbConfirm hardware finish at sampling. A finish change is a new purchase order, and on bags it is the most common cause of a slipped date.