What is your production lead time for jackets & shirts?
A mill delay cannot be recovered by adding sewing capacity.
The shell is woven or dyed to order and arrives before cutting. Once the mill is late, the factory has machines and no fabric — the three weeks of sewing simply starts later.
Rule of thumbIf the date is fixed, pick a shell the mill stocks. If the shell must be woven to order, treat the mill lead time as part of your production lead time.